Legislature(2009 - 2010)SENATE FINANCE 532

03/18/2009 09:00 AM Senate FINANCE


Download Mp3. <- Right click and save file as

Audio Topic
09:07:03 AM Start
09:07:24 AM SB75
10:14:52 AM Adjourn
* first hearing in first committee of referral
+ teleconferenced
= bill was previously heard/scheduled
+= SB 75 BUDGET: CAPITAL, SUPP. & OTHER APPROPS TELECONFERENCED
Heard & Held
University
Department of Education and Early
Development
Department of Public Safety
+ Bills Previously Heard/Scheduled TELECONFERENCED
SENATE BILL NO. 75                                                                                                            
                                                                                                                                
     "An Act  making and amending  appropriations, including                                                                    
     capital  appropriations,  supplemental  appropriations,                                                                    
     and appropriations  to capitalize funds;  and providing                                                                    
     for an effective date."                                                                                                    
                                                                                                                                
9:07:24 AM                                                                                                                    
                                                                                                                                
UNIVERSITY OF ALASKA (UA)                                                                                                     
                                                                                                                                
PETE  KELLY,   DIRECTOR,  STATE  RELATIONS,   UNIVERSITY  OF                                                                    
ALASKA, provided  an overview  of the  university's deferred                                                                    
maintenance  needs  to  provide   context  for  the  capital                                                                    
requests.  The  university  has  approximately  six  million                                                                    
square feet  of facilities,  with nearly 400  buildings, and                                                                    
currently has  around $800 million in  deferred maintenance.                                                                    
The  university has  been averaging  about  $16 million  per                                                                    
year for deferred maintenance; the  amount needed to stay at                                                                    
zero  is approximately  $50 million  per year.  He explained                                                                    
that  the  formula  used   to  determine  major  maintenance                                                                    
requirements  is  1.5  percent  of the  book  value  of  the                                                                    
buildings. Book  value is the  cost of each building  at the                                                                    
time it was built. He  added that facilities personnel would                                                                    
discuss  the deferred  maintenance of  various campuses  via                                                                    
teleconference.                                                                                                                 
                                                                                                                                
Co-Chair Stedman  confirmed that governor's request  was for                                                                    
$8 million, and  that the initial budget  submission was $10                                                                    
million. He  asked about an  amendment reducing  the request                                                                    
by $2 million.                                                                                                                  
                                                                                                                                
MICHELLE RIZK, ASSOCIATE  VICE PRESIDENT, BUDGET, UNIVERSITY                                                                    
OF ALASKA, agreed  that the Office of  Management and Budget                                                                    
(OMB) had requested the university  to reduce the submission                                                                    
in response to the current economic situation.                                                                                  
                                                                                                                                
Ms.  Rizk listed  the projects  included  in the  governor's                                                                    
amended budget.  The first, Maintaining  Existing Facilities                                                                    
Renewal  and Renovation  Annual  Requirement,  is the  first                                                                    
priority of the UA Board  of Regents. The board believes the                                                                    
large inventory  of education buildings must  be maintained.                                                                    
The project extends the life  of the buildings to reduce the                                                                    
need for new construction, and replaces failing buildings.                                                                      
                                                                                                                                
Co-Chair Stedman asked what the  university had received the                                                                    
previous  year. Ms.  Rizk answered  that the  university had                                                                    
received $45.8 million for  renewal and renovation. Projects                                                                    
that  were   funded  included  the  Anchorage   campus  roof                                                                    
replacement,  the  Tanana  Valley campus  exterior  envelope                                                                    
space   revitalization,   the  Fairbanks   campus   critical                                                                    
electrical  distribution, deferred  critical renewal  at the                                                                    
Nome campus, the Anderson Building  renewal in Juneau, and a                                                                    
Ketchikan building roof replacement.                                                                                            
                                                                                                                                
Co-Chair  Stedman  asked  if all  the  deferred  maintenance                                                                    
money had been expended and  the projects finished. Ms. Rizk                                                                    
replied that  all of the FY  09 funding had not  been spent;                                                                    
projects  are in  various  stages  of completion,  including                                                                    
design and pending contracting award.                                                                                           
                                                                                                                                
9:12:58 AM                                                                                                                    
                                                                                                                                
Ms. Rizk moved to the  second item, the University of Alaska                                                                    
Fairbanks  (UAF)  Life   Sciences  Innovation  and  Learning                                                                    
Facility, which  is the board's number  one new construction                                                                    
priority. The  governor's budget  includes $20.6  million of                                                                    
non-general fund; the board  requested $82.2 million general                                                                    
funds as  well. The  facility would provide  modern academic                                                                    
space for more than  600 biology and wildlife degree-seeking                                                                    
students. She pointed out that  a non-general fund component                                                                    
was  added  for  the  bonding capacity  available  with  the                                                                    
research space in the facility.                                                                                                 
                                                                                                                                
Ms. Rizk detailed  the next item, the  UAF Energy Technology                                                                    
Building. The governor's budget includes $15.3 million non-                                                                     
general  fund; the  board's request  includes an  additional                                                                    
$15.3 million  in state funds.  She emphasized  the critical                                                                    
need to  expand research  laboratory space  as the  need for                                                                    
advanced  energy technology  grows. The  fast-track building                                                                    
could  be  completed  20  to  24  months  after  funding  is                                                                    
secured.                                                                                                                        
                                                                                                                                
Ms.  Rizk  turned  to  the  UAF  Fire  Station  and  Student                                                                    
Firefighter Training  Center planning funds.  The governor's                                                                    
budget  includes $500,000  non-general  funds for  planning;                                                                    
the  board's request  includes an  additional $1  million in                                                                    
general funds for planning. The  UAF program is the only one                                                                    
of  its  kind  in  the  country.  Student  firefighters  are                                                                    
treated as full-time career  firefighters and receive hands-                                                                    
on training.                                                                                                                    
                                                                                                                                
Ms. Rizk explained that the  next project deletes UAF Alaska                                                                    
Region Research Vessel  additional receipt authority because                                                                    
the project was moved to the stimulus bill.                                                                                     
                                                                                                                                
9:15:18 AM                                                                                                                    
                                                                                                                                
Ms.  Rizk continued  with the  next item,  an estimation  of                                                                    
potential federal receipt authority  needed for FY10 to FY15                                                                    
projects at  the main and community  campuses. Prior funding                                                                    
in the  category has been  used for projects like  the Sitka                                                                    
welding  lab renovation  and the  Tok center  renovation. In                                                                    
FY08, the university received $15  million; it also received                                                                    
funds in FY04 and FY05 that have been expended.                                                                                 
                                                                                                                                
Ms.  Rizk  turned  to  the   next  project,  the  UA  Energy                                                                    
Projects.  The  governor's  budget includes  $5  million  of                                                                    
federal  receipt  authority.  The  project  is  new  to  the                                                                    
capital  budget  and  would provide  funding  for  alternate                                                                    
energy and energy efficiency projects.  She pointed out that                                                                    
state investment would make  the university more competitive                                                                    
for more federal funding.                                                                                                       
                                                                                                                                
Co-Chair  Hoffman asked  what types  of energy  projects are                                                                    
being considered and  where in the state the  money would be                                                                    
spent.  Ms. Rizk  answered that  the  energy projects  would                                                                    
emphasize alternative  energy and energy  efficiency options                                                                    
ranging   from  small   villages  to   large-scale  regional                                                                    
projects,  including  hydro  and  geothermal  projects.  She                                                                    
directed the committee to a  comprehensive list for details.                                                                    
The receipt authority could be  used in conjunction with the                                                                    
listed projects.                                                                                                                
                                                                                                                                
Co-Chair Hoffman asked what role  the board of regents would                                                                    
play in the decision-making process.                                                                                            
                                                                                                                                
9:17:49 AM                                                                                                                    
                                                                                                                                
Mr.  Kelly answered  that  the board's  role  would be  less                                                                    
directing  the  funds  than  making  decisions  about  state                                                                    
energy  needs.  He pointed  out  that  the Fairbanks  energy                                                                    
program  was  working  closely with  the  governor's  energy                                                                    
authority.   He   provided   the  example   of   wind-diesel                                                                    
operations in  Kotzebue. He did  not know exactly  where the                                                                    
non-general funds would be expended.                                                                                            
                                                                                                                                
Ms. Rizk  described the next  project, UA  Climate Projects.                                                                    
The  governor's  budget  includes  $10  million  of  federal                                                                    
receipt  authority. Projects  funded  would include  natural                                                                    
hazard  monitoring,   improving  weather   predictions,  the                                                                    
Alaska statewide digital  mapping initiative, and permafrost                                                                    
dynamics.                                                                                                                       
                                                                                                                                
Ms. Rizk explained  the next project as the  deletion of the                                                                    
Graduate   Medical   Education/Family   Practice   Residency                                                                    
Program  because  the funding  was  moved  from the  capital                                                                    
budget  to the  operating  budget. Mr.  Kelly added  details                                                                    
regarding the item.                                                                                                             
                                                                                                                                
Ms.  Rizk  discussed  the  final  project,  the  UA  Gasline                                                                    
Workforce Development  request for $1,720,000. The  item was                                                                    
part of the Department of  Labor's gasline request and would                                                                    
support   training  for   any  occupation   utilizing  heavy                                                                    
equipment.  The   item  would  reduce  training   costs  and                                                                    
increase training opportunities in Alaska.                                                                                      
                                                                                                                                
Co-Chair Hoffman requested  more detail regarding university                                                                    
receipts  for  several  of  the  projects.  Ms.  Rizk  asked                                                                    
facilities personnel to provide  detail regarding the source                                                                    
of funds  and receipt  authority for  the UAF  Life Sciences                                                                    
and Learning  Facility, the UAF Energy  Technology Building,                                                                    
and the  UAF Fire  Station and Student  Firefighter Training                                                                    
Center.                                                                                                                         
                                                                                                                                
9:20:34 AM                                                                                                                    
                                                                                                                                
PAT PITNEY, VICE  CHANCELLOR, UNIVERSITY OF ALASKA-FAIRBANKS                                                                    
(testified  via teleconference),  explained  that the  $20.6                                                                    
million listed for the life  sciences facility is university                                                                    
receipt  authority. A  university  bond would  be paid  back                                                                    
based on research growth with  indirect cost recovery; $20.6                                                                    
million  is the  outside  edge of  what  the university  can                                                                    
afford for a facility and  would cover half the construction                                                                    
of  the  research  component. The  state  funding  would  be                                                                    
required to make a usable  building. She emphasized that the                                                                    
facility was the highest priority.                                                                                              
                                                                                                                                
Ms.  Pitney  added  that  the $15  million  for  the  energy                                                                    
facility  would  come  from  the same  source  as  the  life                                                                    
sciences facility, indirect cost  recovery based on research                                                                    
growth  resulting   from  having  faculty  working   in  the                                                                    
building.                                                                                                                       
                                                                                                                                
Co-Chair  Hoffman commented  that  the  university would  be                                                                    
requesting $97 million in general  funds in FY11. Ms. Pitney                                                                    
agreed that  the university bond  funding could only  fund a                                                                    
portion   of  the   facilities.   Unlike  other   university                                                                    
facilities,   the   projects    have   a   university-funded                                                                    
component. In  the past, facility funding  requests have not                                                                    
had this component.                                                                                                             
                                                                                                                                
9:24:16 AM                                                                                                                    
                                                                                                                                
Co-Chair  Hoffman asked  the annual  operating costs  of the                                                                    
facilities. Ms. Pitney responded  that operating costs would                                                                    
be approximately  $2 million for the  life sciences facility                                                                    
and approximately $500,000 for the energy facility.                                                                             
                                                                                                                                
Ms.  Pitney  added  that regarding  the  fire  station,  the                                                                    
university  is a  contractor for  the  Fairbanks North  Star                                                                    
Borough. The  university would look for  partnership funding                                                                    
which  would  also  be university  receipts.  General  funds                                                                    
would be secured before seeking partnership funding.                                                                            
                                                                                                                                
DEPARTMENT OF EDUCATION AND EARLY DEVELOPMENT (DEED)                                                                          
                                                                                                                                
MARK  LEWIS, DIRECTOR,  ADMINISTRATIVE SERVICES,  DEPARTMENT                                                                    
OF EDUCATION AND EARLY DEVELOPMENT,  explained that the FY10                                                                    
budget request  includes an internal request  for $1 million                                                                    
for  the  Mt.  Edgecumbe   High  School  that  will  address                                                                    
deferred  maintenance   items;  the  rest  of   the  capital                                                                    
appropriation would fund the first  23 projects on the major                                                                    
maintenance list published February 19, 2009.                                                                                   
                                                                                                                                
Co-Chair Stedman requested the major maintenance list.                                                                          
                                                                                                                                
9:26:51 AM          AT EASE                                                                                                   
9:27:04 AM          RECONVENED                                                                                                
                                                                                                                                
Co-Chair Stedman  explained that the major  maintenance list                                                                    
is  compiled by  the  department. The  legislature does  not                                                                    
adjust the  list but goes down  the list until the  money is                                                                    
spent.  He  noted  that the  proposed  DEED  capital  budget                                                                    
amount  was $42.4  million for  the current  year for  major                                                                    
maintenance for schools around the state.                                                                                       
                                                                                                                                
Mr. Lewis  reviewed the major maintenance  items, explaining                                                                    
that  the  $42,433,481  appropriation  funds  the  first  23                                                                    
projects on the list:                                                                                                           
                                                                                                                                
    Kaltag   K-12  School   Heating  Systems   Replacement:                                                                  
     $1,780,835                                                                                                                 
    Diomede K-12 School Renovation: $15,896,220                                                                              
    Kodiak Seismic Mitigation Project: $3,236,143                                                                            
    Craig Middle School Classroom Renovation: $83,588                                                                        
    Saint  Marys Districtwide  Fuel Tank  Farm Replacement:                                                                  
     $3,306,502                                                                                                                 
    Craig Elementary School Roof Replacement: $85,807                                                                        
    Kotlik K-12 Heat Plant Relocation: $1,369,015                                                                            
    Aleknagik, Clarks Point, and  Ekwok K-12 HVAC Upgrades:                                                                  
     $384,186                                                                                                                   
    Evergreen    Elementary   School    Playground   Safety                                                                  
     Upgrades: $770,698                                                                                                         
    Kasigluk-Akula  K-12 School  Generation Building  Floor                                                                  
     Failure Repairs: $928,581                                                                                                  
    Galena   Regional  Learning   Center  Dining   Facility                                                                  
     Upgrades: $3,528,598                                                                                                       
    Houghtaling   Elementary  Outdoor   Physical  Education                                                                  
     Shelter Replacement: $276,110                                                                                              
    False Pass K-12 School Siding Replacement: $92,042                                                                       
   Platinum K-12 School Prime Power Generators: $181,678                                                                     
    Allakaket  K-12  School   Water  Systems  Improvements:                                                                  
     $861,994                                                                                                                   
    Saint  Marys   Garage  and  Warm   Storage  Renovation:                                                                  
     $882,608                                                                                                                   
    Galena Regional  Learning Center Gym  Building Upgrade:                                                                  
     $6,888,506                                                                                                                 
    Cold Bay K-12 Heating System Upgrade: $75,789                                                                            
    Craig   Middle  School   Exterior  Envelope   Upgrades:                                                                  
     $26,868                                                                                                                    
    Valley Park Elementary Siding Replacement: $467,164                                                                      
    Huslia High School Exterior Upgrades: $923,685                                                                           
    Pacific High School Renovation: $1,736,513                                                                               
    Sand Point K-12 School Window Replacement: $67,948                                                                       
                                                                                                                                
Co-Chair Stedman  noted that there was  approximately a $453                                                                    
million  backlog  on  the major  maintenance  list,  leaving                                                                    
around $410 million. Several  years previous the legislature                                                                    
had appropriated  around $350 million  and moved  the entire                                                                    
list.   He  assured   the  public   that  the   other  major                                                                    
maintenance  issues would  be addressed  in the  future when                                                                    
there is more money. He  pointed out that the current budget                                                                    
addressed 23 projects out of a list of 138.                                                                                     
                                                                                                                                
Co-Chair Hoffman  asked how  the amount  of $42  million was                                                                    
determined, noting that  the next unfunded item  on the list                                                                    
was a Bethel project. Mr.  Lewis replied that initially DEED                                                                    
had  requested funding  for  the first  20  projects on  the                                                                    
list, based  on the November 8  list. After reconsideration,                                                                    
priorities changed, allowing three more projects.                                                                               
                                                                                                                                
Co-Chair Hoffman asked how the  initial list was determined.                                                                    
Mr. Lewis  answered that  OMB gave DEED  an amount  it could                                                                    
request.                                                                                                                        
                                                                                                                                
9:34:33 AM                                                                                                                    
                                                                                                                                
                                                                                                                                
DEPARTMENT OF PUBLIC SAFETY (DPS)                                                                                             
                                                                                                                                
DAN SPENCER, DIRECTOR,  DIVISION OF ADMINISTRATIVE SERVICES,                                                                    
DEPARTMENT OF  PUBLIC SAFETY, directed the  committee to the                                                                    
department's  list,  beginning   with  Aircraft  and  Vessel                                                                    
Repair and Maintenance.  He explained the item  as an annual                                                                    
request for  routine and emergency  repairs to  aircraft and                                                                    
vessels, which  is relatively expensive. The  department has                                                                    
provided   a  list   showing  the   types  of   repairs  and                                                                    
maintenance that may be necessary;  he noted that priorities                                                                    
could change.                                                                                                                   
                                                                                                                                
Senator Olson asked  how much was appropriated  in FY09. Mr.                                                                    
Spencer  answered  $1  million. Senator  Olson  queried  the                                                                    
number of  airplane accidents during  the year.  Mr. Spencer                                                                    
replied  that   he  would  get   the  information   for  the                                                                    
committee.                                                                                                                      
                                                                                                                                
Co-Chair  Stedman requested  the  information  for the  last                                                                    
three years.                                                                                                                    
                                                                                                                                
Senator  Olson clarified  that his  primary concern  was the                                                                    
number of  airplane and helicopter  accidents over  the past                                                                    
year. He wanted  to see if the department  is addressing the                                                                    
issue of the number of accidents occurring.                                                                                     
                                                                                                                                
Co-Chair  Stedman asked  for the  information  for the  past                                                                    
five years.                                                                                                                     
                                                                                                                                
9:37:51 AM                                                                                                                    
                                                                                                                                
Mr.  Spencer agreed  to provide  the  information and  added                                                                    
that  DPS   conducted  a  lot   of  flight   under  abnormal                                                                    
conditions, particularly  when conducting search  and rescue                                                                    
missions and rural landings for wildlife enforcement.                                                                           
                                                                                                                                
Senator Olson stated that he  was not concerned about search                                                                    
and rescue but other situations that he had witnessed.                                                                          
                                                                                                                                
Mr. Spencer  moved to item  4, $400,000 for  Alaska Wildlife                                                                    
Troopers Law Enforcement Equipment  Replacement, and item 6,                                                                    
$500,000   for  Alaska   State   Troopers  Law   Enforcement                                                                    
Equipment  Replacement.  He noted  that  the  items were  an                                                                    
annual request for routine replacement  of equipment such as                                                                    
snow machines,  outboard motors, firearms,  ballistic vests,                                                                    
and other equipment that wears out on a regular basis.                                                                          
                                                                                                                                
Senator  Huggins asked  for more  information regarding  the                                                                    
purchase of firearms. Mr. Spencer  replied that he would get                                                                    
the information.                                                                                                                
                                                                                                                                
Mr.  Spencer turned  to item  8,  $2 million  for the  final                                                                    
phase of  the Alaska  Public Safety Information  Network. He                                                                    
noted that  the system had  been before the  legislature for                                                                    
different  appropriations  over  the  past  eight  years.  A                                                                    
significant  amount of  federal  funding has  gone into  the                                                                    
program; it  has received more  federal than  state funding.                                                                    
The  department  has  been unable  to  obtain  more  federal                                                                    
funding, so the  amount requested is needed  to complete the                                                                    
project.                                                                                                                        
                                                                                                                                
9:40:22 AM                                                                                                                    
                                                                                                                                
Mr.  Spencer  described  item  12,   $2.5  million  for  the                                                                    
Anchorage   Aircraft  Hangar   Replacement,  Phase   II.  He                                                                    
reminded   the   committee   about  a   prior   $3   million                                                                    
appropriation  for the  project. Subsequent  discussion with                                                                    
the  Department  of  Transportation  and  Public  Facilities                                                                    
(DOT/PF)  revealed  that  the  actual  cost  of  the  needed                                                                    
building  would  be over  $5  million.  He stated  he  would                                                                    
return with further information if the bids come in lower.                                                                      
                                                                                                                                
Senator Olson  asked whether  the project  was in  line with                                                                    
the Anchorage  airport master  plan. Mr.  Spencer understood                                                                    
that the project complied with the master plan.                                                                                 
                                                                                                                                
Senator Olson queried the status  of other hangars that were                                                                    
for  sale.   Mr.  Spencer  answered  that   there  had  been                                                                    
discussion about other hangars but  it was determined that a                                                                    
new hangar  was better. Senator  Olson referred to  a change                                                                    
of  management  in  an aviation  company  that  resulted  in                                                                    
vacated hangars at the airport.                                                                                                 
                                                                                                                                
9:44:12 AM                                                                                                                    
                                                                                                                                
Co-Chair  Stedman  queried  the department's  timeline.  Mr.                                                                    
Spencer  was  not certain.  Co-Chair  Stedman  asked for  an                                                                    
update  on the  information, noting  the radical  changes in                                                                    
economic conditions that may present new opportunities.                                                                         
                                                                                                                                
Senator Olson discussed the location of possible hangars.                                                                       
                                                                                                                                
Senator Huggins asked whether  the department had researched                                                                    
the availability of other hangars.                                                                                              
                                                                                                                                
Mr.  Spencer   noted  that   DPS  had   considered  possible                                                                    
opportunities  presented by  the  changing  status of  Kulis                                                                    
Air; the Kulis  hangar could accommodate some  of the larger                                                                    
aircraft,  but he  believed the  new hangar  would still  be                                                                    
necessary.                                                                                                                      
                                                                                                                                
9:46:41 AM                                                                                                                    
                                                                                                                                
Senator  Huggins questioned  the involvement  of DOT/PF  and                                                                    
expressed concern about the 50  percent increase in the cost                                                                    
of the  project. Mr. Spencer  explained that the  initial $3                                                                    
million request did not include  a formal bid estimate. Once                                                                    
DPS worked with DOT/PF, it  became clear that changes in the                                                                    
economic situation would increase costs.                                                                                        
                                                                                                                                
Senator  Huggins  reiterated  his concerns  and  asked  when                                                                    
DOT/PF would update  the plan. He noted  amendments that had                                                                    
been  made.  Mr. Spencer  responded  that  the estimate  was                                                                    
valid. He was optimistic that  the project could be done for                                                                    
the initial estimate.                                                                                                           
                                                                                                                                
9:49:47 AM                                                                                                                    
                                                                                                                                
Mr.  Spencer  continued with  item  14,  $100,000 for  Crime                                                                    
Laboratory  Equipment   Replacement.  He  stated   that  the                                                                    
department  would like  to  get  regular appropriations  for                                                                    
replacing equipment.  The crime lab equipment  is expensive.                                                                    
He noted that the department  has been searching for federal                                                                    
funds.                                                                                                                          
                                                                                                                                
Mr. Spencer  described item 16,  $1.5 million  for Statewide                                                                    
Facilities  Maintenance,   Repairs,  and   Improvements.  He                                                                    
pointed  out   that  sixty  facilities   including  offices,                                                                    
storage, and  trooper housing require  repair that  is often                                                                    
expensive,   especially   in   emergency   situations.   The                                                                    
department would  like regular  funding to prevent  the need                                                                    
for deferred maintenance.                                                                                                       
                                                                                                                                
Mr. Spencer turned to item  19, $800,000 for Network Storage                                                                    
Servers  and  Software. He  explained  that  the item  would                                                                    
allow the department  to use equipment such  as in-car video                                                                    
systems  that  have  already   been  funded  and  installed.                                                                    
Policing operations  are becoming more  technology-based and                                                                    
Alaska is not keeping pace.                                                                                                     
                                                                                                                                
9:52:36 AM                                                                                                                    
                                                                                                                                
Mr. Spencer detailed item 22,  $480,000 for the Alaska State                                                                    
Trooper  Mobile Data  Computers, Phase  II. He  reminded the                                                                    
committee  of  a  previous $480,000  appropriation  for  the                                                                    
first  phase of  the program  and explained  the use  of the                                                                    
computers used in squad cars and elsewhere in the field.                                                                        
                                                                                                                                
Mr. Spencer moved  to item 24, $240,500 for  the Online Fire                                                                    
and  Life  Safety  Plan  Review   System  Phase  II,  Mobile                                                                    
Systems. The  system was funded  several years  previous and                                                                    
was  near  completion. He  explained  how  the system  would                                                                    
allow  building  inspectors  access to  information  and  to                                                                    
print out reports  in the field. The  system provides better                                                                    
service  to the  customer  and is  more  efficient and  cost                                                                    
effective for the state.                                                                                                        
                                                                                                                                
Mr.  Spencer   explained  item   27,  $220,000   Alaska  Law                                                                    
Enforcement Information  Sharing System  (ALEISS, pronounced                                                                    
"alias")  Support.   The  system   allows  the   sharing  of                                                                    
information among  many state  agencies. He  emphasized that                                                                    
the  system was  not the  same as  the Alaska  Public Safety                                                                    
Information  Network,  an  official repository  of  criminal                                                                    
records  and other  information.  The  ALEISS allows  police                                                                    
agencies  to   share  information.  The  program   has  been                                                                    
federally funded  but that funding  is no  longer available.                                                                    
The department is looking for  a long-term funding solution;                                                                    
the capital request is bridge funding.                                                                                          
                                                                                                                                
9:55:47 AM                                                                                                                    
                                                                                                                                
Senator Huggins asked how many  local entities would be able                                                                    
to  interface with  the system.  Mr.  Spencer answered  that                                                                    
most local agencies would be  able to interface with ALEISS.                                                                    
Senator  Huggins  asked  if  local  agencies  paid  for  the                                                                    
interface.  Mr. Spencer  thought  the  agencies already  had                                                                    
interface  capability.  The  request   is  to  maintain  the                                                                    
system. He offered to get details.                                                                                              
                                                                                                                                
Senator  Huggins pointed  out that  if the  expense was  for                                                                    
upkeep  of the  system it  should  be an  operating and  not                                                                    
capital request. Mr.  Spencer opined that the  item could go                                                                    
either  way.  He  questioned whether  the  request  for  the                                                                    
current year would fall into  a fiscal year, as required for                                                                    
the operating budget.                                                                                                           
                                                                                                                                
Senator  Huggins asked  if DPS  would return  with the  same                                                                    
request the  following year. Mr.  Spencer answered  that the                                                                    
department did not  expect to be back for  the item. Senator                                                                    
Huggins asked  how the system  would then be  supported. Mr.                                                                    
Spencer explained that the item  is not currently in the DPS                                                                    
budget because  ALEISS is overseen  by a consortium  [of law                                                                    
enforcement  agencies]  which   has  been  getting  on-going                                                                    
federal funding. The funding is  no longer available, so the                                                                    
department  looking for  on-going  funding.  The request  is                                                                    
only a bridge until  additional, non-state funding is found.                                                                    
He  emphasized the  importance of  ensuring funding  for the                                                                    
program. He stated that the  department would take advantage                                                                    
of other opportunities.                                                                                                         
                                                                                                                                
9:58:27 AM                                                                                                                    
                                                                                                                                
Senator Huggins reiterated concerns  about the request being                                                                    
for operational and not capital costs.                                                                                          
                                                                                                                                
Co-Chair Stedman asked the department to look at the issue.                                                                     
                                                                                                                                
Mr.  Spencer  turned  to  item  29,  $200,000  for  Computer                                                                    
Replacements. The department wants  to have a regular system                                                                    
for  replacing computers,  some of  which are  obsolete. The                                                                    
item would  fund needed  replacement of  one quarter  of DPS                                                                    
computers, which should happen on an annual basis.                                                                              
                                                                                                                                
Mr.  Spencer  detailed  item 30,  $125,000  for  the  Alaska                                                                    
Wildlife Troopers Navigation Data  Storage Project. The item                                                                    
would build  a data base of  information regarding important                                                                    
sites around  the state, including remote  landing sites for                                                                    
wildlife patrol  and search  and rescue  missions. Currently                                                                    
the department relies  on the local knowledge  of whoever is                                                                    
assigned.  A   new  trooper  or  other   search  and  rescue                                                                    
personnel  would have  access  to a  stockpile of  important                                                                    
information. He pointed out that  the item was ranked on the                                                                    
priority list.                                                                                                                  
                                                                                                                                
Co-Chair  Stedman suggested  expanding  the  program to  let                                                                    
experienced  wildlife troopers  mark marine  locations where                                                                    
there  is  aggressive  sport activity.  New  troopers  could                                                                    
benefit from  the accumulated knowledge of  more experienced                                                                    
troopers.                                                                                                                       
                                                                                                                                
10:01:43 AM                                                                                                                   
                                                                                                                                
Co-Chair  Stedman  referred  to   the  Sitka  Public  Safety                                                                    
Training  Academy  and  pointed  to  community  support  for                                                                    
expanding   the  academy   and  adding   a  driving   range.                                                                    
Reasonable  expansion of  the academy's  land base  could be                                                                    
accomplished by  taking advantage  of the closing  of nearby                                                                    
Sheldon Jackson  Community College. Mr. Spencer  stated that                                                                    
DPS  strongly supports  the driving  range in  Sitka as  the                                                                    
current situation not good.                                                                                                     
                                                                                                                                
Co-Chair  Hoffman asked  how Village  Public Safety  Officer                                                                    
(VPSO) equipment  got replaced.  Mr. Spencer  responded that                                                                    
the  VPSO equipment  has  been replaced  in  the past  using                                                                    
leftover  funds.  Federal  rural law  enforcement  equipment                                                                    
funds have also been used.                                                                                                      
                                                                                                                                
Co-Chair Hoffman  emphasized that the VPSOs  needed the same                                                                    
consistent funding as  troopers and should not  have to rely                                                                    
on  leftover  funds. He  did  not  want the  village  public                                                                    
safety program treated as a stepchild of the department.                                                                        
                                                                                                                                
10:05:38 AM                                                                                                                   
                                                                                                                                
Co-Chair Stedman noted  that in FY09, $600,000  had been put                                                                    
in the budget  for the driving range,  but the appropriation                                                                    
was cut.  The committee  had been  told that  the department                                                                    
would request $3  million for the driving range  in FY10. He                                                                    
understood that declining revenues  affected the choice, but                                                                    
he  wanted  to take  advantage  of  the opportunity  of  the                                                                    
available adjacent  land. He asked the  department to return                                                                    
to the committee with more information.                                                                                         
                                                                                                                                
Senator Olson  asked if  there was  an academy  in Fairbanks                                                                    
for law enforcement  training. Mr. Spencer did  not know but                                                                    
offered to find out.                                                                                                            
                                                                                                                                
Mr.  Spencer  turned  to  item   31,  $2.5  million  federal                                                                    
receipts for  the Marine  Fisheries Patrol  Improvements. He                                                                    
explained that  DPS has a  joint enforcement  agreement with                                                                    
the  National  Marine  Fisheries  Service.  He  referred  to                                                                    
discussion  as  to  whether  the   item  should  be  in  the                                                                    
operating or capital budget. Some  of the funds are used for                                                                    
capital expenditures that cross fiscal years.                                                                                   
                                                                                                                                
Co-Chair  Stedman  asked  if the  item  included  monitoring                                                                    
illegal  fishing activities.  Mr. Spencer  responded in  the                                                                    
affirmative and added that the item funds dockside checks.                                                                      
                                                                                                                                
10:09:06 AM                                                                                                                   
                                                                                                                                
Co-Chair  Stedman  emphasized  the   need  for  more  active                                                                    
wildlife  policing  in   Southeast  Alaska,  especially  for                                                                    
illegal  fishing; there  is  very  little protection  unless                                                                    
there  is a  specific complaint.  He expressed  frustration.                                                                    
Mr. Spencer noted his concerns.                                                                                                 
                                                                                                                                
Senator Huggins queried  the status of the crime  lab on the                                                                    
capital priority list  and the current cost  estimate of the                                                                    
lab.  Mr.  Spencer  responded  that the  lab  is  still  the                                                                    
department's top  priority. The  lab has been  designed, but                                                                    
questions  were raised  regarding the  size of  the facility                                                                    
and a study was contracted  for. A report was generated, but                                                                    
questions remain;  DPS is still assessing  the situation. He                                                                    
did not  know whether  a request for  the facility  would be                                                                    
forthcoming. The  department would  like to have  a request,                                                                    
but it recognizes legislative  and public concerns regarding                                                                    
the  appropriateness   of  the  size  of   the  facility  as                                                                    
designed.                                                                                                                       
                                                                                                                                
Co-Chair Stedman asked  for an update on the  report as well                                                                    
as more information regarding  site development. He referred                                                                    
to concerns about the expense of delaying development.                                                                          
                                                                                                                                
10:14:10 AM                                                                                                                   
                                                                                                                                
Mr.  Spencer understood  that the  final agreement  with the                                                                    
municipality  of Anchorage  included  a  provision that  the                                                                    
municipality would buy the site  at market value if the site                                                                    
is developed but does not go forward.                                                                                           
                                                                                                                                
SB 75 was HEARD and HELD in Committee for further                                                                               
consideration.                                                                                                                  
                                                                                                                                
10:14:52 AM                                                                                                                   
                                                                                                                                

Document Name Date/Time Subjects
DEED FY10FinalMaintList.pdf SFIN 3/18/2009 9:00:00 AM
SB 75
DEED FY10FinalConstructionList.pdf SFIN 3/18/2009 9:00:00 AM
SB 75
Univ R&R List $8 Mill FY2010.pdf SFIN 3/18/2009 9:00:00 AM
SB 75